We know that many of you backed the project over 2 years ago and we anticipated being where we are today, a year ago. We weren’t willing to compromise on reliability, and when reliability testing showed that some components failed after a few thousand espressos, we re-sourced those components until we got a machine that could reliably brew over 10,000 back-to-back espressos without issue. Those extra design cycles added a year to the process that we hadn’t anticipated. Thank you to the many Backers that encouraged us to ‘get it right’.
We began building and shipping the certified, mass production espresso machines to Backers in Mid-September. This was the start of our first 1,000 unit manufacturing batch and we don’t yet know how long it will take to build them all. As we gain experience, we expect to be able to build and test more machines every week, with a goal of 250 units per week. As of November, we are averaging between 50 and 100 units per week, and perform thorough testing before sending them to Backers.
We know how impatient many of you are to get your machines, and we’re doing everything we can to deliver them as quickly as possible. With 4,000 backers, the best case scenario is that we will deliver all machines by Q2 2026, although later backers could receive their machines in Q3 or Q4. Much will depend on the manufacturing capacity from our manufacturing partner, and the throughput we can maintain without risking quality.